Case Studies
The Argyle Cut
Concrete removal using the wire saw... more »
Chatswood to Epping Rail tunnel
Precision drilling of 96,000 high tolerance holes...more »
The Cross City Tunnel
Tunnel joint venture constructors, Baulderstone ... more »
Hinze Dam Alliance
Removal of existing structure to allow construction... more »
Port Hedland Iron ore car dumper
Large scale concrete removal using the wire saw... more »
Refurbishment of the Bulga Coal Singleton Coal Feeder
Modifications to Feeder No.4 required the removal of heavily... more »
Sydney International Airport
Precision cutting of bearing pads and footings in existing slabs... more »
Urra Dam Structural Remodification
Wire sawing to remove sections of spillway to allow... more »
The Argyle Cut
CLIENT
NSW RailCorp
PROJECT
The Argyle Cut
PROJECT DESCRIPTION
Concrete removal using the wire saw
PROJECT DURATION
January 2007
PROJECT VALUE
$27,000
DOWNLOAD
BACKGROUND
The NSW Rail Corporation required an emergency exit door installed in the concrete tunnel wall of the Shore Down Line, close to the Argyle Portal, which forms part of freeway approach to the Sydney Harbour Bridge.
The tunnel wall is 1.2m thick and the opening needed to be 1.5m wide by 2.2m high.
KEY CHALLENGES
The floor of the tunnel was found to be 670mm lower than the outside ground level, so the top and bottom cuts had to cut on an angle of 28° from horizontal.
A further complication was that the concrete had to be cut and lifted out and the opening made safe in a 40 hour closure from 6am Saturday to 10.00pm Sunday.
As the project was taking place in Observatory Park in central Sydney, the working area had to be fenced o and fail-safe slurry control measures implemented.
Various signal and communication cable ducts were within 100mm of the planned top of the opening.
All personnel had to be RailCorp Track Awareness inducted, and stringent Occupational Health and Safety precautions observed.
PROJECT METHODOLOGY
150mm diameter lifting holes were drilled and used to check the construction drawings and to verify the height difference of 670mm;
Four 150mm diameter corner holes were drilled on the 28° angle, and two 50mm diameter intermediate holes were drilled horizontally;
Two side cuts were made, followed by the sloping bottom cut, the horizontal middle cut and the sloping top cuts using a wire saw;
A 20 tonne crane was used to remove the two pieces of concrete weighing just under 10 tonnes in total.
PROJECT SUCCESSES
With the cutting finished and concrete removed we cut and formed stairs and fitted a door before leaving the site clean and secure well before the Sunday deadline!