Case Studies
The Argyle Cut
Concrete removal using the wire saw... more »
Chatswood to Epping Rail tunnel
Precision drilling of 96,000 high tolerance holes...more »
The Cross City Tunnel
Tunnel joint venture constructors, Baulderstone ... more »
Hinze Dam Alliance
Removal of existing structure to allow construction... more »
Port Hedland Iron ore car dumper
Large scale concrete removal using the wire saw... more »
Refurbishment of the Bulga Coal Singleton Coal Feeder
Modifications to Feeder No.4 required the removal of heavily... more »
Sydney International Airport
Precision cutting of bearing pads and footings in existing slabs... more »
Urra Dam Structural Remodification
Wire sawing to remove sections of spillway to allow... more »
Sydney International Airport
CLIENT
FORD CIVIL CONTRACTING
PROJECT
Sydney International Airport
PROJECT DESCRIPTION
Precision cutting of bearing pads and footings in existing slabs
PROJECT DURATION
January - April 2008
PROJECT VALUE
$180,000
DOWNLOAD
BACKGROUND
Combined Saw Cutting was engaged by Ford Civil to cut over fifty 1.8m x 1.8m and 2m x 2m square pads through 500mm thick concrete to allow footings to be prepared for piles.
These piles would form the footings for a new retail shopping area and baggage handling facility at the Sydney International Airport as well as the crane bearing pads to be used during construction.
KEY CHALLENGES
Structural engineers were concerned that any over cuts in the mass concrete slab would generate uncontrolled cracking throughout the slab, which would necessitate complete removal and reinstatement of the concrete slab.
All pads had to be completely cut through the concrete whilst ensuring there were no over cuts at the corners.
PROJECT SUCCESSES
Combined developed a new methodology which proved three times quicker and more cost effective than the traditional solution of stitch core drilling each corner.
This methodology ensured each slab was able to be lifted cleanly and could be loaded directly onto waiting trucks for removal from the site.
All pad cuts were completed cleanly with no over cutting or cracking and work finalised two days ahead of schedule.
Copyright © 2009 Combined Saw Cutting
Website Design & Hosting by Planet HomePage
